ENEA Operator Poznań
Task: Development concept and supplies for the ENEA Data Centre
Project:
The subject was the selection and delivery of fully equipped 4DC server racks (26 pcs.) with the development and integration with CyberRow targeted cooling air-conditioning units from STULZ. The racks were equipped with IP power distribution units (52 pcs.)
ICT connections in the kiosk were provided as follows: optical fibre technology using OM4 optical fibre cables terminated with LC connectors in telescopic optical distribution frames.
Copper connections – Class EA based on BKT 695 Cat 7 cable
(Delivery of copper and optical fibre patch cables).